Research · Energy → Compute

Who is actually powering compute

AI and bitcoin mining are now buying power at utility scale. Not every headline is a contract. We track the deals behind the theme, check each one against its source, and separate binding commitments from letters of intent and frameworks.

66
deals tracked
31.2 GW firm power offtake in 32 power-supply deals
49
signed or in service
22.2 GW of firm power offtake signed or in service
49
listed companies involved
53
listed companies screened

GW adds up firm generation capacity in power-supply deals only. Caps and options are left out, and so are data-center IT load (3.4 GW more in 12 hosting deals), equipment and solar peak capacity, which are measured differently.

The market at a glance

These charts count deals rather than megawatts, so deals stated in different units sit side by side.

Deals made public per quarter

By the date a deal first appeared in a source. The latest quarter is to date.

Q2
2025
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
Q4
2026
Signed or in service Announced, non-binding or sold

Who is buying

Direct counterparty. Fluidstack deals carry a Google backstop.

  • Google11
  • Meta8
  • Amazon / AWS5
  • Brookfield4
  • Fluidstack4
  • Microsoft3
  • CoreWeave3
  • Oracle2
  • Others17
  • Undisclosed9

What powers it

Energy source named in the deal; “unknown” where the source doesn’t say.

  • Gas17
  • Nuclear10
  • Renewables9
  • Mixed3
  • Hydro2
  • Unknown25

Energy-to-Compute deal tracker

Large North American and global deals where power, fuel or power equipment goes to compute, each checked against its primary source. Capacity is shown in the unit the deal states. MW of generation, IT load and equipment are different things, so we only add up like with like.

Data as of November 6, 2026Download CSV

Cite as: PermianChain, Energy-to-Compute Deal Tracker, data as of November 6, 2026, permianchain.com/research/energy-to-compute/

Segment
Status
66 of 66 deals
  • 2026-11-06
    Announced / non-bindingasset: development

    Invitium Energy (PPL 51% / Blackstone Infrastructure JV)NYSE: PPL

    QTS Data Centers (Blackstone)private (Blackstone: NYSE: BX)

    2,000 MW generation

    JV/development · Energy supply · unknown · 20 yr

    Salem Township, Pennsylvania, US

    filing

  • 2026-11-05
    Signed

    Bloom EnergyNYSE: BE

    NTT DATA (NTT Global Data Centers)

    900 MW equipment

    equipment supply · Power infrastructure · unknown

    global (sites not named)

    press release

  • 2026-11-05
    Announced / non-bindingasset: development

    BKV-BPP Power (BKV Corporation JV)NYSE: BKV

    Undisclosed leading frontier AI lab

    400 MW generation

    other · Energy supply · unknown

    Temple, Texas, US

    filing

  • 2026-11-05
    Announced / non-binding

    EvergyNASDAQ: EVRG

    Digital RealtyNYSE: DLR

    framework cap 1,400 MW campus (none firm)

    other · Energy supply · unknown

    Evergy Kansas/Missouri service territory, US

    filing

  • 2026-11-04
    Signedasset: development

    Riot PlatformsNASDAQ: RIOT

    Anthropicprivate

    910 MW IT load

    hosting conversion · Compute on owned power · unknown · 15 yr

    Corsicana Facility, Navarro County, Texas, US

    filing

  • 2026-11-03
    Announced / non-bindingasset: development

    Drax GroupLSE: DRX

    Brookfield / Radiant (via Brookfield-Qai AI infrastructure JV)NYSE: BAM

    framework cap 1,000 MW campus (100 firm)

    JV/development · Energy supply · mixed

    Drax Power Station, North Yorkshire, UK

    press release

  • 2026-10-22
    Signed

    INNIO (Jenbacher)NASDAQ: INIO

    Undisclosed leading U.S. developer/operator of mega-scale data center campuses

    620 MW equipment

    equipment supply · Power infrastructure · gas

    US

    press release

  • 2026-10-22
    Signed

    Voltusprivate

    GoogleNASDAQ: GOOGL

    1,070 MW demand response

    other · Energy supply · mixed

    PJM region, US

    press release

  • 2026-10-22
    Announced / non-bindingasset: development

    Araicoprivate

    Crusoe (Crusoe Cloud)private

    up to 280 MW IT load (106 firm)

    JV/development · Compute on owned power · hydro

    adjacent to the Itaipú substation, Paraguay

    press release

  • 2026-10-21
    Announced / non-binding

    Liberty Energy (Liberty Power Innovations)NYSE: LBRT

    Undisclosed leading frontier AI lab (with a dedicated infrastructure platform)

    1,200 MW generation

    on-site generation contract · Energy supply · unknown

    US data center campuses (sites not named)

    filing

  • 2026-10-21
    Signedasset: development

    Kinder Morgan (Natural Gas Pipeline Company of America)NYSE: KMI

    Undisclosed A-rated hyperscaler

    Not disclosed

    other · Energy supply · gas

    Permian Basin, Texas, US

    filing

  • 2026-10-21
    Signedasset: development

    Kinder MorganNYSE: KMI

    Undisclosed data center and industrial customers

    Not disclosed

    other · Energy supply · gas

    Central Texas, US

    filing

The value chain, in three segments

Each company sits in one segment, by business model, and is tested on whether energy for compute is material to that business, not whether it is mentioned in a press release.

Energy supply

Producers, utilities, independent power producers, nuclear and renewables, midstream, and owner-operators of power plants built for data centers.

Materiality test
E2C power as a share of owned capacity, or E2C revenue as a share of revenue: at least 5%.

Power infrastructure

Manufacturers and EPC firms delivering turbines, engines, fuel cells, boilers and on-site power systems to data centers. Backup generation is tracked separately.

Materiality test
Data-center revenue or backlog as a share of the total: at least 10%.

Compute on owned power

AI/HPC and bitcoin-mining operators whose capacity runs on power they generate, take behind the meter, or hold under a site-specific supply contract.

Materiality test
Capacity with dedicated power as a share of total capacity: at least 50%.

How we judge the evidence

EvidenceCounts?
Signed contract, operating asset, recognised revenueYes
Binding obligation with routine conditions still open (permits, site selection)Yes, flagged conditional
LOI, MOU, non-binding framework, option, “up to” cap, management targetNo: watchlist only
  • Dedicated power means site-specific capacity a company generates itself, takes behind the meter, or holds under an executed interconnection or supply agreement. Studies, approvals and owning a substation are not enough.
  • Same basis or a lower bound. A ratio compares like with like: same unit, scope and date. Where a company reports on mixed bases, it has to pass on the most conservative combination.
  • Missing data is missing. We don't estimate. A company without the disclosures to test is recorded as insufficient evidence, not as a pass or a fail.
  • Point in time. Every figure keeps its public date and source, so any past state can be rebuilt.

We are building a rules-based Energy-to-Compute index on this evidence base. Constituents and index levels are not published yet.

Go deeper

Where you fit

Scope, sources and corrections

  • Deals first made public from May 2025 onwards (plus one from April 2025), checked against company filings, releases and news reports, October 2026. Only deals whose source shows a data-center or compute buyer or use are listed.
  • “First public” is the earliest date the deal appeared in a source we opened. Status reflects the latest update we found.
  • This is research, not investment advice, and not an offer of any financial product.
  • Spotted an error, or a deal we should add? Write to contact@permianchain.com.