Tools · Gas-to-Bitcoin netback

What is your gas worth: pipeline or bitcoin?

Netback is what the operator keeps per unit of gas after costs. Compare selling into the sales pipeline at the AECO price with using the gas on site to generate power and mine bitcoin.

Gas
Btu/scf

1 mcf ≈ 1.087 GJ

Currency

1 USD = 1.4000 CAD (2026-10-28)

Pipeline sale
CAD/GJ

Default: AECO daily price C$2.04/GJ on 2026-11-22 (Gas Alberta).

CAD/GJ
CAD/GJ

Pipeline route only

On-site bitcoin mining
CAD/GJ

Generator, miners, operations, hosting share

%
TH/s
W
%

Pipeline netback

C$1.54 /GJ

C$1,674 per day · C$50,875 per month

Sales price − lifting − marketing & transport

Bitcoin netback

C$10.61 /GJ

C$11,535 per day · C$350,664 per month

Mining revenue − lifting − on-site costs

Mining earns more per GJ by

C$9.07 /GJ · C$299,789 per month

On-site costs are set to zero, so the bitcoin netback leaves out generator, miner, operating and hosting costs. Enter them for a fair comparison.

Gas energy
1,087 GJ/day
Average power
4.40 MW
Miners supported
1,197
Bitcoin mined
0.1054 BTC/day
Mining revenue
C$11,807/day
Revenue per GJ
C$10.86/GJ

Bitcoin network: price US$80,000, difficulty 140.6 T, reward 3.140 BTC/block (as of 2026-10-28; live data unavailable).

Is your site worth a closer look? Send us the basics and our team will assess on-site bitcoin mining or AI compute for your gas.

Request a site assessment

Site assessment

Turn this estimate into a real project

PermianChain develops and operates on-site power and compute for gas producers. Tell us about your site and our team will check whether it warrants a technical and commercial evaluation.

Your information is reviewed by the PermianChain team for initial commercial and technical qualification.

How it works

  • Pipeline netback = gas sales price − lifting cost − marketing & transportation cost, per GJ.
  • Bitcoin netback = mining revenue per GJ − lifting cost − on-site costs. Gas burned at the wellsite pays no pipeline transport.
  • Mining revenue: the gas runs a generator at the efficiency entered (35% is typical for reciprocating engines); the power runs miners (plus 5% for cooling and power conversion); expected bitcoin = hashrate × time × block reward ÷ (difficulty × 2³²), less the pool fee, at the live bitcoin price.
  • Default sales price: the AECO daily price published by Gas Alberta, in CAD per GJ, refreshed when the site is updated. Enter your own contract price at any time. CAD/USD comes live from mempool.space.
  • Costs can be entered per GJ or per mcf at the heating value above. On-site costs start at zero: add your generator, miner, operations and hosting costs for a realistic comparison.
  • A planning estimate, not an engineering or investment conclusion. Difficulty rises and the bitcoin price moves daily.