Wazalishaji 20 katika nchi 6 ambao wametumia gesi kwenye maeneo yao kuzalisha umeme papo hapo kwa ajili ya uchimbaji wa bitcoin au uwezo wa kompyuta wa AI na HPC, 5 kati yao wakiwa hai. Kutokana na matangazo ya umma, nyaraka rasmi na tafiti kifani; kila kipengele kina kiungo cha chanzo chake. Pale ambapo mzalishaji anaonekana katika data ya uchomaji, tunaonyesha jinsi uchomaji wake katika nchi hiyo ulivyobadilika tangu mradi uanze: ni muktadha, si uthibitisho kwamba mradi ndio uliosababisha mabadiliko hayo.
Miradi
Hali
Matumizi
Miradi 20 kati ya 20
ExxonMobil (XTO Energy)pilot
Part of ExxonMobil (NYSE: XOM)
Bakken, North Dakota (Jorgenson Deep Creek site reported), United States
Mshirika
Crusoe Energy
Matumizi
bitcoin mining
Gesi
flare
Uwezo
—
Tangu
2021-01
Uchomaji unaohusishwa na ExxonMobil katika United States: 0.483 bcm (2020) → 0.376 bcm (2025), −22%.
Up to 18 MMcf/month of gas; Exxon weighed expanding to Alaska, Nigeria, Argentina, Guyana, Germany (2022). No later status published.
Bakken, North Dakota (two-well pad without pipeline), United States
Mshirika
Crusoe Energy
Matumizi
bitcoin mining
Gesi
flare
Uwezo
—
Tangu
2019
Uchomaji unaohusishwa na Chord Energy katika United States: 0.789 bcm (2018) → 0.111 bcm (2025), −86%.
Crusoe release (Aug 2019) quotes Enerplus VP: two-well pilot raised gas capture ~400,000 cf/d. Still listed as Crusoe client Oct 2021. Enerplus acquired by Chord Energy 2024 (wb_name = successor).
New Era Helium (now New Era Energy & Digital)announced
NASDAQ: NUAI
Ector County near Odessa, Permian Basin, United States
Mshirika
Sharon AI (JV Texas Critical Data Centers)
Matumizi
AI/HPC
Gesi
unknown
Uwezo
250 MW
Tangu
2025-01
Gas-fired plant plus CCS on gas supplied by New Era's Permian production (agreement under negotiation); site uses gas transmission line, so not strictly on the wellsite. Target 100 MW by Dec 2026; Texas permit freeze Sep 2026 may delay.
Engine No. 1 / GE Vernova (end user reported: Microsoft)
Matumizi
AI/HPC
Gesi
unknown
Uwezo
2,500 MW
Tangu
2027
Uchomaji unaohusishwa na Chevron katika United States: 0.144 bcm (2025) → 0.144 bcm (2025), +0%.
Off-grid gas plant fed by Chevron's own Permian gas; ~2.5 GW initial, expandable to 5 GW; power targeted 2027. Large grid-bypass power plant, not flare capture.
Los Toldos II Este, Vaca Muerta, Neuquén, Argentina
Mshirika
Unblock (Crusoe data centers)
Matumizi
bitcoin mining
Gesi
flare
Uwezo
12 MW
Tangu
2023-12
Uchomaji unaohusishwa na Tecpetrol katika Argentina: 0.004 bcm (2022) → 0.004 bcm (2025), mpya.
Signed Jun 2023; 8 x 1.5 MW Jenbacher gensets (12 MW) on ~50,000 m3/d, operating since Dec 2023. Let extended well testing go ahead (oil 50 to 300 m3/d). Columbia CCSI/Capterio case study, Jun 2025.
YPF (UTE Bajo del Toro: YPF, Equinor, YPF Luz)active
JV: YPF (BYMA: YPFD · NYSE: YPF)
Bajo del Toro thermal plant, Rincón de los Sauces, Neuquén (Vaca Muerta), Argentina
Mshirika
Genesis Digital Assets (GDA)
Matumizi
bitcoin mining
Gesi
flare
Uwezo
7.00 MW
Tangu
2024-05
Uchomaji unaohusishwa na YPF katika Argentina: 0.314 bcm (2023) → 0.315 bcm (2025), +0%.
7 MW installed plus 1 MW backup (some outlets say 8 MW) on flare gas from YPF operations; GDA data center inside the plant. Reports disagree on 1,200 vs 12,000 miners.
Uchomaji unaohusishwa na NNPC katika Nigeria: 0.417 bcm (2024) → 0.505 bcm (2025), +21%.
Gas Connection Agreement under Nigerian Gas Flare Commercialisation Programme; civil works started; aimed for 2 sites live by end-2025, no energization confirmed. wb_name is NNPC parent (JV partner, not operator).